NSW has approved Snowy 2.0. Here are six reasons why that’s a bad move



Lucas Coch/AAP

Bruce Mountain, Victoria University and Mark Lintermans, University of Canberra

The controversial Snowy 2.0 project has mounted a major hurdle after the New South Wales government today announced approval for its main works.

The pumped hydro venture in southern NSW will pump water uphill into dams and release it when electricity demand is high. The federal government says it will act as a giant battery, backing up intermittent energy from by wind and solar.

We and others have criticised the project on several grounds. Here are six reasons we think Snowy 2.0 should be shelved.

1. It’s really expensive

The federal government announced the Snowy 2.0 project without a market assessment, cost-benefit analysis or indeed even a feasibility study.

When former Prime Minister Malcolm Turnbull unveiled the Snowy expansion in March 2017, he said it would cost A$2 billion and be commissioned by 2021. This was revised upwards several times and in April last year, Snowy Hydro awarded a A$5.1 billion contract for partial construction.

Snowy Hydro has not costed the transmission upgrades on which the project depends. TransGrid, owner of the grid in NSW, has identified options including extensions to Sydney with indicative costs up to A$1.9 billion. Massive extensions south, to Melbourne, will also be required but this has not been costed.

The Tumut 3 scheme, with which Snowy 2.0 will share a dam.
Snowy Hydro Ltd

2. It will increase greenhouse gas emissions

Both Snowy Hydro Ltd and its owner, the federal government, say the project will help expand renewable electricity generation. But it won’t work that way. For at least the next couple of decades, analysis suggests Snowy 2.0 will store coal-fired electricity, not renewable electricity.

Snowy Hydro says it will pump the water when a lot of wind and solar energy is being produced (and therefore when wholesale electricity prices are low).




Read more:
Snowy 2.0 is a wolf in sheep’s clothing – it will push carbon emissions up, not down


But wind and solar farms produce electricity whenever the resource is available. This will happen irrespective of whether Snowy 2.0 is producing or consuming energy.

When Snowy 2.0 pumps water uphill to its upper reservoir, it adds to demand on the electricity system. For the next couple of decades at least, coal-fired electricity generators – the next cheapest form of electricity after renewables – will provide Snowy 2.0’s power. Snowy Hydro has denied these claims.

Khancoban Dam, part of the soon-to-be expanded Snowy Hydro scheme.
Snowy Hydro Ltd

3. It will deliver a fraction of the energy benefits promised

Snowy 2.0 is supposed to store renewable energy for when it is needed. Snowy Hydro says the project could generate electricity at its full 2,000 megawatt capacity for 175 hours – or about a week.

But the maximum additional pumped hydro capacity Snowy 2.0 can create, in theory, is less than half this. The reasons are technical, and you can read more here.

It comes down to a) the amount of time and electricity required to replenish the dam at the top of the system, and b) the fact that for Snowy 2.0 to operate at full capacity, dams used by the existing hydro project will have to be emptied. This will result in “lost” water and by extension, lost electricity production.



The Conversation, CC BY-ND

4. Native fish may be pushed to extinction

Snowy 2.0 involves building a giant tunnel to connect two water storages – the Tantangara and Talbingo reservoirs. By extension, the project will also connect the rivers and creeks connected to these reservoirs.

A small, critically endangered native fish, the stocky galaxias, lives in a creek upstream of Tantangara. This is the last known population of the species.

The stocky galaxias.
Hugh Allan

An invasive native fish, the climbing galaxias, lives in the Talbingo reservoir. Water pumped from Talbingo will likely transfer this fish to Tantangara.

From here, the climbing galaxias’ capacity to climb wet vertical surfaces would enable it to reach upstream creeks and compete for food with, and prey on, stocky galaxias – probably pushing it into extinction.

Snowy 2.0 is also likely to spread two other problematic species – redfin perch and eastern gambusia – through the headwaters of the Murrumbidgee, Snowy and Murray rivers.




Read more:
Snowy 2.0 threatens to pollute our rivers and wipe out native fish


5. It’s a pollution risk

Snowy Hydro says its environmental impact statement addresses fish transfer impacts, and potentially serious water quality issues.

Four million tonnes of rock excavated to build Snowy 2.0 would be dumped into the two reservoirs. The rock will contain potential acid-forming minerals and other harmful substances, which threaten to pollute water storages and rivers downstream.

When the first stage of the Snowy Hydro project was built, comparable rocks were dumped in the Tooma River catchment. Research in 2006 suggested the dump was associated with eradication of almost all fish from the Tooma River downstream after rainfall.

Snowy 2.0 threatens to pollute pristine Snowy Mountains rivers.
Schopier/Wikimedia

6. Other options were not explored

Many competing alternatives can provide storage far more flexibly for a fraction of Snowy 2.0’s price tag. These alternatives would also have far fewer environmental impacts or development risks, in most cases none of the transmission costs and all could be built much more quickly.

Expert analysis in 2017 identified 22,000 potential pumped hydro energy storage sites across Australia.

Other alternatives include chemical batteries, encouraging demand to follow supply, gas or diesel generators, and re-orienting more solar capacity to capture the sun from the east or west, not just mainly the north.

Where to now?

The federal government, which owns Snowy Hydro, is yet to approve the main works.

Given the many objections to the project and how much has changed since it was proposed, we strongly believe it should be put on hold, and scrutinised by independent experts. There’s too much at stake to get this wrong.




Read more:
Five gifs that explain how pumped hydro actually works


The Conversation


Bruce Mountain, Director, Victoria Energy Policy Centre, Victoria University and Mark Lintermans, Associate professor, University of Canberra

This article is republished from The Conversation under a Creative Commons license. Read the original article.

Advertisement

Snowy 2.0 threatens to pollute our rivers and wipe out native fish



Schopier/Wikimedia

John Harris, UNSW and Mark Lintermans, University of Canberra

The federal government’s Snowy 2.0 energy venture is controversial for many reasons, but one has largely escaped public attention. The project threatens to devastate aquatic life by introducing predators and polluting important rivers. It may even push one fish species to extinction.

The environmental impact statement for the taxpayer-funded project is almost 10,000 pages long. Yet it fails to resolve critical problems, and in one case seeks legal exemptions to enable Snowy 2.0 to wreak environmental damage.

The New South Wales government is soon expected to grant the project environmental approval. This process should be suspended, and independent experts should urgently review the project’s environmental credentials.

Native fish extinctions

Snowy Hydro Limited, a Commonwealth-owned corporation, is behind the Snowy 2.0 project in the Kosciuszko National Park in southern NSW. It involves building a giant tunnel to connect two water storages – the Tantangara and Talbingo reservoirs. By extension, the project will also connect the rivers and creeks connected to these reservoirs.

A small, critically endangered native fish, the stocky galaxias, lives in a creek upstream of Tantangara. This is the last known population of the species.




Read more:
Snowy 2.0 is a wolf in sheep’s clothing – it will push carbon emissions up, not down


An invasive native fish, the climbing galaxias, lives in the Talbingo reservoir (it was introduced from coastal streams when the original Snowy project was built). Water pumped from Talbingo will likely transfer this fish to Tantangara.

From here, the climbing galaxias’ capacity to climb wet vertical surfaces would enable it to reach upstream creeks and compete for food with, and prey on, stocky galaxias – probably pushing it into extinction.

The stocky galaxias.
Hugh Allan

Snowy Hydro has applied for an exemption under NSW biosecurity legislation to permit the transfer of the climbing galaxias and two other fish species: the alien, noxious redfin perch and eastern gambusia.

Redfin perch compete for food with other species and produce many offspring. They are voracious, carnivorous predators, known to prey on smaller fish.

Redfin perch also allow the establishment of a fatal fish disease – epizootic haematopoietic necrosis virus – or EHN. This disease kills the endangered native Macquarie perch, the population of which below Tantangara is one of very few remaining.

If Snowy 2.0 is granted approval, it is likely to spread these problematic species through the headwaters of the Murrumbidgee, Snowy and Murray rivers.

The climbing galaxias, which threatens the native stocky galaxias.
Stella McQueen/Wikimedia

Acid and asbestos pollution

Four million tonnes of rock excavated to build Snowy 2.0 would be dumped into the two reservoirs. Snowy Hydro has not assessed the pollution risks this creates. The rock will contain potential acid-forming minerals and a form of asbestos, which threaten to pollute water storages and rivers downstream.

When the first stage of the Snowy Hydro project was built, comparable rocks were dumped in the Tooma River catchment. Research in 2006 suggested the dump was associated with eradication of almost all fish from the Tooma River downstream after rainfall.




Read more:
Snowy 2.0 will not produce nearly as much electricity as claimed. We must hit the pause button


Addressing the problems

The environmental impact statement either ignores, or pays inadequate attention to, these environmental problems.

For example, installing large-scale screens at water inlets would be the best way to prevent fish transfer from Talbingo Dam, but Snowy Hydro has dismissed it as too costly.

Snowy Hydro instead proposes a dubious second-rate measure: screens to filter pumped flows leaving Tantangara reservoir, and building a barrier in the stream below the stocky galaxias habitat.

The best and cheapest way to prevent damage from alien species is stopping the populations from establishing. Trying to control or eradicate pest species once they’re established is far more difficult and costly.



The Conversation, CC BY-ND

We believe the measures proposed by Snowy Hydro are impractical. It would be very difficult to maintain a screen fine and large enough to prevent fish eggs and larvae moving out of Tantangara reservoir and such screens would be totally ineffective at preventing the spread of EHN virus.

A six metre-high waterfall downstream of the stocky galaxias habitat currently protects the critically endangered species from other invasive species threats. But climbing galaxias have an extraordinary ability to ascend wet surfaces. They would easily climb the waterfall, and possibly the proposed creek barrier as well.

Such an engineered barrier has never been constructed in Australia. We are informed that in New Zealand, the barriers have not been fully effective and often require design adjustments.




Read more:
The government’s electricity shortlist rightly features pumped hydro (and wrongly includes coal)


Even if the barrier protected the stocky galaxias at this location, efforts to establish populations in other unprotected regional streams would be severely hampered by the spread of climbing galaxias.

Preventing redfin and EHN from entering the Murrumbidgee River downstream of Tantangara depends on the reservoir never spilling. The reservoir has spilled twice since construction in the 1960s, and would operate at much higher water levels when Snowy 2.0 was operating. Despite this, Snowy Hydro says it has “high confidence in being able to avoid spill”.

If dumped spoil pollutes the two reservoirs and Murrumbidgee and Tumut rivers, this would also have potentially profound ecological impacts. These have not been critically assessed, nor effective prevention methods identified.

The Tumut 3 scheme, part of the existing Snowy Hydro scheme.
Snowy Hydro Ltd

Looking to the future

Snowy 2.0 will likely make one critically endangered species extinct and threaten an important remaining population of another, as well as pollute freshwater habitats. As others have noted, the project is also questionable on other environmental and economic grounds.

These potential failures underscore the need to immediately halt Snowy 2.0, and subject it to independent expert scrutiny.


In response to the issues raised in this article, a spokesperson for Snowy Hydro said:

“Snowy Hydro’s EIS, supported by numerous reports from independent scientific experts, extensively address potential water quality and fish transfer impacts and the risk mitigation measures to be put in place. As the EIS is currently being assessed by the NSW Government we have no further comment.”


A previous version of this article incorrectly stated that water pumped from Tantangara will likely transfer fish to Talbingo. It should have said water pumped from Talbingo will likely transfer fish to Tantangara.The Conversation

John Harris, Adjunct Associate Professor, Centre for Ecosystem Science, UNSW and Mark Lintermans, Associate professor, University of Canberra

This article is republished from The Conversation under a Creative Commons license. Read the original article.

Snowy 2.0 is a wolf in sheep’s clothing – it will push carbon emissions up, not down



Luka Cochleae/AAP

Bruce Mountain, Victoria University

The massive Snowy 2.0 pumped hydro project is soon expected to be granted environmental approval. I and others have criticised the project on several grounds, including its questionable financial viability and overstated benefits to the electricity system. But Snowy 2.0’s greenhouse gas emissions have barely been discussed.

Both Snowy Hydro and its owner, the federal government, say the project will help expand renewable electricity generation (and by extension, contribute to emissions reduction from the energy sector).

However, closer inspection shows it won’t work that way. For at least the next couple of decades, Snowy 2.0 will store coal-fired electricity, not renewable electricity. In fact, I predict Snowy 2.0 will create additional demand for coal-fired generation and lead to an increase in greenhouse gas emissions for the foreseeable future.

Khancoban Dam, part of the soon-to-be expanded Snowy Hydro scheme.
Snowy Hydro Ltd

The problem explained

The expanded Snowy Hydro scheme in southern New South Wales will involve pumping water uphill to a reservoir, storing it, and then releasing it downhill to generate electricity when demand is high.

The emissions reduction potential of the project rests on what type of electricity is used to pump the water uphill. Snowy Hydro says it will pump the water when a lot of wind and solar energy is being produced (and therefore when wholesale electricity prices are low).

But the crucial point here is that wind and solar farms produce electricity whenever the resource is available. This will happen irrespective of whether Snowy 2.0 is producing or consuming energy.




Read more:
Snowy 2.0 will not produce nearly as much electricity as claimed. We must hit the pause button


When Snowy 2.0 pumps water uphill to its upper reservoir, it adds to demand on the electricity system. The generators that will provide this extra electricity are the ones that would not operate unless Snowy 2.0’s pumping demand was calling them into operation.

These will not be renewable generators since they will be operating anyway. Rather, for the next couple of decades at least, coal-fired electricity generators – the next cheapest form of electricity after renewables – will provide Snowy 2.0’s power.

Snowy Hydro claims Snowy 2.0 will add 2000 megawatts of renewable capacity to the national electricity market. However Snowy 2.0 is a storage device, and its claim to be renewable rests on the source of the electricity that it stores and then reproduces. It is not renewable electricity that Snowy 2.0 will store and reproduce for the foreseeable future.

The Snowy 2.0 scheme will lead to more coal use in the foreseeable future.
Julian Smith/AAP

Why this matters

Ageing coal-fired generaters will account for a smaller share of Australia’s electricity production over time as they become uneconomic and close down. But projections from the Australian Energy Market Operator show coal will make up a significant proportion of electricity production for the next two decades.

It is only when all coal-fired generators have closed (and gas-fired generators have not taken their place) that Snowy 2.0 could claim to be using renewable electricity to power its pumps.

Does this matter? Yes, very much. Using Snowy Hydro’s projections of how much
electricity Snowy 2.0 will pump each year from 2025 to 2047 (the period over which they have developed their projections) I estimate that Snowy 2.0 will, on average, account for 5.4 million tonnes of carbon dioxide equivalent each year.




Read more:
Turnbull unveils Snowy plan for pumped hydro, costing billions


This is clearly a big number – roughly equivalent to the annual greenhouse gas emissions of Australia’s mineral or chemical industry, and equal to the annual emissions of 2.4 million cars.

If we assume, conservatively, that emissions have a cost of A$20 per tonne of carbon, then Snowy 2.0 will impose an additional annual cost of A$108 million on the Australian community that will need to be countered by emissions reduction somewhere else in the economy.

Over 20 years, Snowy 2.0 will lead to more greenhouse gas emissions than three million cars.
Julian Smith/AAP

The NSW government has adopted a target of net-zero emissions by 2050. But using Snowy Hydro’s projections of pumped energy, average greenhouse gas emissions attributable to Snowy 2.0 over its first decade will increase NSW’s emissions by about 10% of their current levels each year.

This proportion will increase if the government successfully reduces emissions elsewhere.

Of course, emission reduction is not just an issue for the states. The federal
government has been at pains to affirm its commitment to the Paris climate accord. Snowy 2.0 will undermine the achievement of this commitment.

If additional energy storage is needed to stabilise our electricity grid, it can be provided by many alternatives with a much smaller greenhouse gas impact such as demand response, gas or diesel generators, batteries or smaller and more efficient pumped-hydro generators.

Meeting the climate challenge

Emissions associated with storage is given little attention in Australia but is well-researched overseas. Since Australia’s state and federal governments profess a commitment to reducing greenhouse gas emissions, this is a serious omission.




Read more:
If the NBN and Snowy Hydro 2.0 were value for money, would we know?


Energy storage will increase emissions as long as fossil fuel generators dominate the power system.

In meeting the climate challenge, greenhouse gas emissions must become a more prominent consideration in the planning and approval of all electricity projects, including storage – and especially for Snowy 2.0.


In response the points raised in this article, Snowy Hydro said Snowy 2.0 would add 2,000 megawatts (MW) of renewable capacity to the national electricity market (NEM).

“In the absence of Snowy 2.0, the NEM will have to fill the capacity need with other power stations, which would inevitably be fossil-fuelled,” the company said in a statement.

“Snowy will sell capacity contracts (tantamount to insurance against NEM price volatility and spikes) to a range of NEM counterparties, as it does now and has done for decades.”

Snowy Hydro said Snowy 2.0 would directly draw wind and solar capacity into the NEM, via the contract market.

It said this market, rather than the wholesale market, drives investment and electricity generation.

“Snowy Hydro’s renewable energy procurement program, through which Snowy contracted with 888 MW of wind and solar facilities in 2019, has made the construction of eight new wind and solar projects possible,” Snowy Hydro said.

“In the NEM, what happens subsequently to the spot price is of little interest to the owners of these facilities, because their revenue is guaranteed through their offtake contracts with Snowy.”

The company said the energy produced by wind and solar plants, backed by Snowy’s existing large-scale generation fleet, was “the most cost-effective and reliable way to serve the customers of the NEM in the future.”

Snowy Hydro said Snowy 2.0 would pump water uphill using cheap electricity from wind and solar – often most plentiful when NEM prices are low – rather than expensive electricity from coal.

“The water is released when prices are high – this is one of the four Snowy 2.0 revenue streams,” it said.

“Given that Snowy has the water storage capability to pump when electricity prices are low, and generate when electricity prices are high, why would Snowy choose to buy expensive coal-fired energy to pump water uphill at times of high prices?”The Conversation

Bruce Mountain, Director, Victoria Energy Policy Centre, Victoria University